McLane Generator Replacement

Carrollton

McLane Generator Replacement

McLane Generator Replacement project details
Project NameLocationGeneral ContractorArchitect / EngineerCompletion DateProject Category
McLane Generator ReplacementCarrollton, TXAmber ElectricalAmber ElectricalSeptember 2025Service

Overview

  • Timeline: Priced in 2022, completed September 2025
  • Delivery Method: 100% Design-Build by Amber
  • Engineering: Engineered drawings developed in coordination with EE; additional designs for switchgear pad and generator pad

Scope of Work

  • Demolition of three existing generators and 50-year-old paralleling gear
  • Installation of 3000A Service-Rated Transfer Switch and 3000A Switchgear
  • Installation of one 500kW generator, with full capability for paralleling with future units
  • Completion of coordination study and arc flash analysis
  • Load bank testing and integration of remote monitoring system

Execution

Amber crews performed the installation within a four-day outage window, working continuously to maintain schedule. Temporary UPS and trailer-mounted generator were deployed to protect the customer’s IDF room, maintaining uninterrupted operation throughout the transition.

Obstacles

  • Had to keep the IT room running during the shutdown
  • Around-the-clock work
  • Testing of Gen, Switchgear and Transfer switch in off hours
  • City of Carrollton
  • Logistics of old and new equipment