Carrollton
McLane Generator Replacement
Carrollton
McLane Generator Replacement
| Project Name | Location | General Contractor | Architect / Engineer | Completion Date | Project Category |
|---|---|---|---|---|---|
| McLane Generator Replacement | Carrollton, TX | Amber Electrical | Amber Electrical | September 2025 | Service |
Overview
- Timeline: Priced in 2022, completed September 2025
- Delivery Method: 100% Design-Build by Amber
- Engineering: Engineered drawings developed in coordination with EE; additional designs for switchgear pad and generator pad
Scope of Work
- Demolition of three existing generators and 50-year-old paralleling gear
- Installation of 3000A Service-Rated Transfer Switch and 3000A Switchgear
- Installation of one 500kW generator, with full capability for paralleling with future units
- Completion of coordination study and arc flash analysis
- Load bank testing and integration of remote monitoring system
Execution
Amber crews performed the installation within a four-day outage window, working continuously to maintain schedule. Temporary UPS and trailer-mounted generator were deployed to protect the customer’s IDF room, maintaining uninterrupted operation throughout the transition.
Obstacles
- Had to keep the IT room running during the shutdown
- Around-the-clock work
- Testing of Gen, Switchgear and Transfer switch in off hours
- City of Carrollton
- Logistics of old and new equipment