Wafer Handling System project details
Project NameLocationGeneral ContractorArchitect / EngineerCompletion DateProject Category
Wafer Handling SystemDallas, TXConfidentialConfidentialNovember 2026Mission-Critical

Overview

Services at facility to support the installation of new nitrogen purge bins serving semiconductor manufacturing operations. The project included new 120V electrical circuits, conduit, receptacles, and power connections across multiple floors, along with labeling and commissioning assistance.

Scope of Work

  • Power Circuits: Installed new 20-amp, 120V electrical services from existing panels and junction boxes to designated purge bin locations.
  • Conduit & Raceway: Replaced specified armored cable routing with EMT conduit above raised floors and installed conduit from purge bin cabinets to overhead storage bays.
  • Receptacles: Installed quad receptacles inside new purge bin cabinets.
  • Electrical Connections: Installed cable and breakers at designated panel spaces and completed wire connections using Polaris connectors where specified.
  • Energized Work: Performed designated energized electrical installations in accordance with the project requirements.
  • Labeling: Installed electrical identification labels to match existing facility labeling methods.
  • Commissioning Support: Assisted with power commissioning for the new purge bin installations.
  • Multi-Floor Installation: Completed electrical work at designated purge bin locations on the first, second, and third floors.